-Sarah Adler
Many students were quite confused as they rounded the corner
on
Westbank Drive the first day of school and found the entire parking lot
next to the office entrance completely fenced off. But this is only one
of the many changes introduced this year.
“All of these changes are part of a bond package approved by
voters two years ago,” principal Linda Rawlings said.
“It
includes renovations on the library, the FAF [Fine Arts Facility], and
the athletic facilities.”
The library is one of the major projects under construction,
scheduled to be completed by the start of the next school year.
“A new hallway connecting the library to the Ninth Grade
Center
will be built where the current entryway is,” head librarian
Carolyn Foote said. “It will be a glass hallway that runs
along
the side of the library. The roof is going to be raised and windows
will be added in the central section of the library, and most of the
brick on the outside will become windows as well. We’re
trying to
use recycled materials where we can and natural materials
elsewhere.”
Because of a request from Foote, there will be a recycling
center in
the eating-friendly section of the new library. The floor plans are
designed so that it will be open, but there will still be plenty of
places to study or learn in a group.
“We’ll have two new computer labs, a media
production
area for video editing, and have wireless internet,” Foote
said.
“The idea is to make the new library as transparent as
possible,
more connected to the campus, and wired for the future.”
In addition to that, the FAF will be completely redone.
“Most of the construction will be about ADA
[Americans with
Disabilities Act] compliance, but other than that it’s just
cosmetic things such as new chairs and doors,” FAF director
Adam
Bernstein said. “We are also upgrading our technical system
to
make it more up-to-date and flexible. All of this should, in turn, make
a better theater production and environment.”
Neither the library, built back in 1969, nor the FAF have been updated
recently, so all of the changes are simply “bringing it up to
standard,” according to Rawlings.
After all of these improvements, the school is also adding a
new
choir hall at the top of the hill behind the Chap Court. Choir students
currently practice in the lecture halls next to the FAF, which is an
inconvenience for the singers, as well as for others who need the FAF
seats.
“With the new choir building, we will finally have a
place of our own,” junior JJ Picone said.
It will also be more technologically advanced and help the
choir with their rehearsals.
“I look forward to the improvements,”
choir director
Edward Snouffer said. “The room will be outfitted with sound
equipment that will allow us to record and evaluate our
rehearsals.”
The construction site is so difficult to access that cranes
will be
used. Because traffic is prohibited from that area, the entire parking
lot by the office is inaccessible. With that closure, the
administration was forced to move visitor parking over by the Chap
Court. Those spots, in addition to those needed for Information
Systems, now occupy about 60 spots that had previously been available
for students.
“What the students need to remember is that I opened
up
parking around a circular drive with a gravel road off the regular
parking in the Ben Hur [junior] lot and added probably about 50 or 60
spots that we didn’t have last year,” Rawlings
said.
“At the end of the day, we probably have just as many parking
spots as we did last year, it’s just not paved.”
Approximately 300 new spots in the Ben Hur lot will be
created on
the land between Ben Hur and Capital of Texas Highway which is owned by
EISD.
In addition, the athletic facilities are also being updated.
The
main gym, basketball locker room bathrooms, the dugout on the baseball
field, the football stadium, and the fields by the Ninth Grade Center
are all either being repainted, redone or reconstructed. However, there
is always more that can be done.
“We do wish that the separate referendum for an
indoor
practice facility for all activities had passed,” Athletic
Events
and Facilities Coordinator Lisa Schlimgen said. “As we have
seen
already this year with the large amount of rain we had in August, a
facility like this would be utilized by many extracurricular programs
at Westlake High School.”
Overall, with the $53 million bond package, the school is
being
brought up to the high standards set for it and getting upgraded out of
the ‘70s.
“I’m excited about the
renovations,” sophomore
Stephanie Collinge said. “I think it will make Westlake a
better
place.”